The Trail to Nowhere. Radio Silence With The Capital

The trouble with the City of Fullerton’s Public Records Act system is that responses are so dilatory, so frequently incomplete, and often so non-responsive, as Friends have seen over the years, it’s hard to know if you can draw any firm conclusions from what are charitably called public records.
Here’s an interesting request made a couple of weeks ago.

The request has elicited a “full release” response, so we may infer, I hope, that it really is full.

Why is this request interesting? Because the obscure State Department of Natural Resources is the grant-giving sugar daddy of the 2.1 million dollar UP Trail fiasco.
I noted back on January 27th that there were problems with the Trail to Nowhere project schedule, namely, that the design and construction milestones were seven and five months late, respectively.

It’s hard to know the exact status of this boondoggle because nobody in City Hall is saying anything about it to the public. I (confidently) assume the final design was never submitted to the State because the City Council never approved it, never released a bid or awarded a contract. Construction has obviously not started. Now there are just eight months left to do it all.

This is where the PRA request comes in. The response just shares a short email string between Fullerton and Natural Resource Department people trying to set up a meeting for a briefing on some water project up north and its impact on MWD cities’ water supply. That’s it. There is nothing about the grant for the so-called UP Trail.

So what is the status? Were the milestones waived by the Natural Resources Department? Has some schedule modification been made? If so there’s no correspondence (at least none shared by the City Clerk) that show it. That’s pretty odd, isn’t it? Is it possible the State isn’t even keeping track of the agreement and the City isn’t bothering to remind them? That strikes a believable chord.

At this point it seems highly unlikely that the Trail to Nowhere could be completed in time, but maybe hope springs eternal. The State doesn’t seem to care.
Ahmad Zahra and his pal Shana Charles made a big deal about this dumbassery and organized such an annoying Astroturf backing for it, that the previous council majority chickened out and agreed to the mess. They haven’t been talking about it either, even though they already took a victory lap and threw themselves a party.
Let’s hope so.
California is broke. Claw back the money. Fullerton doesn’t want to be on the hook maintaining a trail no one is going to bother to use. Egleth cried about the importance of Pacific Drive Park and how many years they “worked” on it. Doesn’t matter that she only used the park for its dedication and photo op for the Observer.
It’s about a healthy mind in a healthy body.
*Capitol
Capital.
Yes, it could be that everyone has given up. It may be because the original budget left out so much stuff that the thing can’t be built for the grant amount.
One thing we know for sure: it wouldn’t be because nobody would use it.