Elevators to Nowhere – The Death March Isn’t Over

It may have been expensive, but it sure was unnecessary…

Two years ago FFFF ran a series of posts based on the observations of “Fullerton Engineer” about the ludicrous elevators addition to the existing bridge at the Depot. Nobody wanted this project except for city staff and only because the dime was somebody else’s. And so a strange bureaucratic odyssey began with fits and starts of activity to waste $4,000,000 of transit money doled out by distant agencies. Then in 2017 the monster was shocked back to life with an infusion of $600,000 of Fullerton’s own cash. Ouch. Let’s let our Friend, Fullerton Engineer take it from here:

It appears as if the depot elevator project is grinding to a conclusion: the elevator foundations and steel are finally done and the traction elevators are almost complete. Are congratulations in order? Not quite, although I suspect there will be a victory celebration and ribbon cutting and back-pats all around when the City Council takes its first expensive elevator ride.

A construction sequence that should have taken perhaps seven months has dragged on for two years. That’s right – two years. No one in charge seems to have offered any explanation, probably because no one in authority has ever asked for any. As I noted in the spring of 2017, the request for more money was shrouded in double talk and obscurantism. Somebody was hiding something.

Over the past two years as I have driven by the site it was more likely that I saw no one working as when I did. So what were all those people who were being paid, and well paid, to oversee this fiasco doing? Who knows? Have delay claim change orders ever been processed? Have they been rejected? Is a lawsuit coming or is it just going to end in a feeding frenzy on a complicit public agency? PRA requests may shed light on this disaster, if in fact they are not ignored by the city’s lawyer.

Don Hoppe, our former City Engineer has disappeared into a well-pensioned retirement. His replacement, a professionally unqualified bureaucrat will take no heat for this embarrassment. It’s no-fault government  where the taxpayer foots the bill.

— The Fullerton Engineer

 

Elevators to Nowhere – The Rising Cost Hits Fullerton Directly

Here’s the final (for now) installment of the series by our Friend “Fullerton Engineer” documenting the sad history of the project to add a couple of elevators to the existing tower/bridge structure at the DepotRemarkably, none of our elected representatives seems the least bit curious about the downward trajectory of this project, or the ultimate tap into our Facility Capital Repair Fund, a fund that was never intended to pay for new construction, particularly for projects never needed in the first place.  

The best way of avoiding embarrassing information is not to ask embarrassing questions. It’s not their money.

It may have been expensive, but it sure was unnecessary…

It took over five years, but the astonishingly high cost of an elevator addition project at the Fullerton train station finally hit Fullerton taxpayers directly in 2017.

The project that the public never asked for and doesn’t need was initiated based not on necessisity, but on the availability of money from Sacramento; and later, OCTA came to the funding rescue. But the delays piled up – year after year, and OCTA would no longer pay the bill. So in March, the City Engineer, Don Hoppe, came hat in hand and asked the Fullerton taxpayers for money. Lots of it. Here’s the staff report.

Notice how the various and diverse issues are all thrown together into a single sum – $600,000. We see added cost for the railroad flagging for some unexplained reason; the curiosity of “unforeseen” utilities on a well-developed site; an unknown amount to pay for the escalated cost of the elevator subcontractor; and finally, an unspecified amount to cover “additional assistant (sic) in contract administration” a nebulous term, but a category clearly meant to cover the ongoing cost of someone in the Public Works department.  The final item is particularly ironic given the amounts already contracted with private companies for construction support and management on this very small project.

The simple fact that these items are lumped together can only be explained by an attempt to obfuscate the nature and trues costs of the ongoing delay. And those delay costs are increasing even now, as the project seems to have stalled again.

— Fullerton Engineer

Elevators to Nowhere – Construction Begins! Oh, Wait. No It Doesn’t.

Friends, here is another in a series of posts about Fullerton’s ill-fated “Elevators to Nowhere” series by “Fullerton Engineer”

It may have been expensive, but it sure was unnecessary…

In following the trajectory of the new elevator project at the Fullerton train station I have described a project that the public neither wanted nor needed, that had its genesis in the simple availability of “free money” way back in 2011 – six long years ago.

Although the design contract was let in 2013, the project was not bid until 2015 when the low bid came in 22% higher than anticipated. The construction contract was awarded anyway. With numerous ancillary “management” contracts, the project budget had grown to $4,000,000. By 2017 that figure had ballooned to an astonishing $4,600,000.

And yet construction didn’t start until February, 2016 and when it did it was only for some minor ADA toilet room modifications adjacent to the AMTRAK ticket office.

Woodcliff Billing #1

You can see in the project billing submitted by Woodcliff Corporation, the contractor, a few items related to bonds, mobilization and the bathroom work in February 2016 – a year after the contract bid. Nothing was billed against the elevator items at all, except for crediting the structural steel shop drawings for $55,000. Over 14 months later the structural steel has not been erected. In fact, the foundations for the steel structure haven’t even been built, as the site sits empty with minor demolition having taken place and some lighting conduit rerouted.

If any delay claims have been submitted by Woodcliff, those documents have not been shared, although delay claims are certainly coming, and escalation costs are already starting to accrue, although we don’t know how much because the costs were intentionally lumped together with  other completely unrelated items in the March 2017 staff report.

As I noted in an earlier post the cause of all these delays is not known by the public because the Public Works staff doesn’t want the public to know that things have obviously gone wrong, very wrong; and, that the inexplicable and unexplained delays have finally cost the taxpayers of Fullerton directly. The money is no longer free.

— Fullerton Engineer

 

 

 

State Auditor Rains on Pringle’s High Speed Rail Parade

Pay no attention to that man in front of the curtain...

In a comprehensive indictment of the High Speed Rail Authority’s procedures and protocols, and its abilities to manage and oversee spending public bond revenue, the California State Auditor has taken a considerable step in derailing the proposed boondoggle. Read the highlights for yourself.

Although this doesn’t tell us anything we didn’t suspect, it does confirm the worst suspicions about poor planning and lax or non-existent oversight, and raises the worst spectre of all: a worthless, duplicative, hyper-expensive and disruptive system – a mere leg – say from Anaheim to downtown Los Angeles.

Tonight Pringle’s PR consultants are coming to town, not to ask our opinion about anything, rest assured. Rather they are coming to soft sell what’s already been decided. But there’s no reason why we can’t go and share our opinions, and maybe even ask Mayor Bankhead (who’s bound to be there) how come he stood up a couple years ago and told people that the City of Fullerton supports this disaster in the making.

They’re going to be at the Senior Center from 5-8 with a propaganda presentation at 6pm.